How to calculate concrete
- Get cubic feet. Length × width × thickness, all in feet.
- Divide by 27. A cubic yard is 3 × 3 × 3 = 27 cubic feet.
- Add 5–10% extra. Running short with a truck on site is expensive.
- Round up to the plant's increment. Many plants sell in quarter yards; ask yours.
Worked example: a 24 × 24 ft garage floor, 5 inches thick
- Volume: 24 × 24 × (5 ÷ 12) = 240.0 cu ft = 8.89 cubic yards.
- Plus 5%: 9.33 cubic yards.
- Rounded up to the quarter yard, order 9.50 cubic yards: about one truck.
Cubic yards by area and thickness
| Area | 4 in | 5 in | 6 in |
|---|---|---|---|
| 100 sq ft | 1.23 | 1.54 | 1.85 |
| 200 sq ft | 2.47 | 3.09 | 3.70 |
| 300 sq ft | 3.70 | 4.63 | 5.56 |
| 400 sq ft | 4.94 | 6.17 | 7.41 |
| 500 sq ft | 6.17 | 7.72 | 9.26 |
| 750 sq ft | 9.26 | 11.57 | 13.89 |
| 1,000 sq ft | 12.35 | 15.43 | 18.52 |
No waste included: add 5–10% before ordering.
Concrete formulas by shape
All measurements in feet; divide inches by 12 first. Results are in cubic feet.
- Slab
- length × width × thickness
- Round slab
- π × (diameter ÷ 2)² × thickness
- Continuous footing
- total length × width × depth
- Pad footing
- length × width × depth × number of footings
- Monolithic slab
- length × width × thickness + perimeter band × (edge depth − thickness), where perimeter band = length × width − (length − 2 × edge width) × (width − 2 × edge width)
- Bell footing
- π × r² × pier height + π × bell height ÷ 3 × (R² + R × r + r²), with r = pier radius and R = bell radius
- Wall
- length × height × thickness
- Column / pier
- π × (diameter ÷ 2)² × height
- Post hole
- (hole area − post area) × depth; round hole π × (diameter ÷ 2)², square hole width²
- Tube / ring
- π × [(outer ÷ 2)² − (inner ÷ 2)²] × height
- Curb & gutter
- [curb depth × (curb height + flag thickness) + gutter width × flag thickness] × length
- Steps (solid, n steps)
- width × rise × run × (1 + 2 + … + n). With a landing, the landing is the top step: width × rise × [run × (1 + … + (n − 1)) + landing depth × n]
Cubic yards = cubic feet ÷ 27.
Frequently asked questions
How do I convert square feet to cubic yards of concrete?
Multiply square feet by the thickness in feet, then divide by 27. At 4 inches: square feet ÷ 81.
What is a short-load fee?
Plants often have a minimum load, commonly around 8–10 cubic yards. Below it they charge a fee for each missing yard, which can make a 1-yard order cost far more per yard than a full truck.
How much concrete fits in a truck?
Standard mixer trucks carry around 8–10 cubic yards; bigger jobs need more than one truck. Ask the plant for their exact size.
How much extra should I order?
5–10%. For ready-mix the plant cannot top you up easily, so err on the high side.