How to calculate concrete
- Add up the length. Measure every run of footing and add them together, in feet.
- Width and depth in inches. Divide by 12 to get feet.
- Multiply. Total length × width × depth gives cubic feet.
- Convert and add extra. Divide by 27 for yards and add 5–10%: trenches are rarely perfectly square.
Worked example: 9 pad footings for a deck, 24 × 24 × 12 in
- One footing: 2 × 2 × 1 = 4 cu ft. Nine footings: 36 cu ft.
- Plus 10% (dug holes are never square): 39.6 cu ft = 1.47 cubic yards.
- In 80 lb bags: 66 bags in total (8 if you buy for each footing separately).
Concrete per 10 feet of footing
| Width × depth | Cubic feet | Cubic yards | 80 lb bags |
|---|---|---|---|
| 12 × 6 in | 5.00 | 0.19 | 9 |
| 16 × 8 in | 8.89 | 0.33 | 15 |
| 20 × 8 in | 11.11 | 0.41 | 19 |
| 20 × 10 in | 13.89 | 0.51 | 24 |
| 24 × 12 in | 20.00 | 0.74 | 34 |
Per 10 linear feet, no waste included.
Concrete per square pad footing
| Footing | Depth | Cubic feet | 80 lb bags | 60 lb bags |
|---|---|---|---|---|
| 16 × 16 in | 8 in | 1.19 | 2 | 3 |
| 16 × 16 in | 12 in | 1.78 | 3 | 4 |
| 18 × 18 in | 8 in | 1.50 | 3 | 4 |
| 18 × 18 in | 12 in | 2.25 | 4 | 5 |
| 20 × 20 in | 8 in | 1.85 | 4 | 5 |
| 20 × 20 in | 12 in | 2.78 | 5 | 7 |
| 24 × 24 in | 8 in | 2.67 | 5 | 6 |
| 24 × 24 in | 12 in | 4.00 | 7 | 9 |
| 30 × 30 in | 8 in | 4.17 | 7 | 10 |
| 30 × 30 in | 12 in | 6.25 | 11 | 14 |
| 36 × 36 in | 8 in | 6.00 | 10 | 14 |
| 36 × 36 in | 12 in | 9.00 | 15 | 20 |
One footing, no waste included.
Concrete formulas by shape
All measurements in feet; divide inches by 12 first. Results are in cubic feet.
- Continuous footing
- total length × width × depth
- Pad footing
- length × width × depth × number of footings
- Monolithic slab
- length × width × thickness + perimeter band × (edge depth − thickness), where perimeter band = length × width − (length − 2 × edge width) × (width − 2 × edge width)
- Column / pier
- π × (diameter ÷ 2)² × height
- Bell footing
- π × r² × pier height + π × bell height ÷ 3 × (R² + R × r + r²), with r = pier radius and R = bell radius
Cubic yards = cubic feet ÷ 27.
Frequently asked questions
How big should a footing be?
It depends on the load, the soil and the frost depth where you live, so the size comes from your plans or building department. The calculator only needs the dimensions.
How do I calculate concrete for a pier footing?
Use π × radius² × depth, in feet, times the number of piers. Choose "Column / pier" in the calculator.
Should I order extra for a footing?
Yes. Dug trenches are irregular and soak up more concrete than the drawing suggests; 10% extra is a safe start.
About the prices
Costs are estimated ranges with source and date, never a quote. Enter your local prices under "Use your own prices", or read how we estimate prices.