How to calculate concrete
- Work out the volume. Length × width × thickness in feet gives cubic feet; ÷ 27 for cubic yards.
- Multiply by the weight per volume. Normal concrete is about 2,400 kg per cubic metre, or about 1,837 kg per cubic yard.
- Convert to tonnes. Divide kilograms by 1,000.
- Check the load. Compare with what your trailer, truck or floor is rated for.
Worked example: a 12 × 20 ft patio, 4 inches thick
- Volume: 12 × 20 × (4 ÷ 12) = 80.0 cu ft, 2.96 yd³ or 2.27 m³.
- Weight: 80.0 cu ft × 150 lb = 12,000 lb, that is 5,443 kg, about 5.4 tonnes.
- The calculator adds your waste percentage to the volume, so its weight is a little higher.
Concrete weight by volume
| Cubic yards | Cubic metres | Kilograms | Tonnes |
|---|---|---|---|
| 0.25 | 0.19 | 459 | 0.5 |
| 0.50 | 0.38 | 919 | 0.9 |
| 1.00 | 0.76 | 1,837 | 1.8 |
| 2.00 | 1.53 | 3,674 | 3.7 |
| 3.00 | 2.29 | 5,511 | 5.5 |
| 5.00 | 3.82 | 9,185 | 9.2 |
| 10.00 | 7.65 | 18,370 | 18.4 |
Normal concrete at 2,403 kg per m³ (150 lb per cu ft).
Weight of a concrete slab
| Thickness | kg per sq ft | lb per sq ft | 10 × 10 ft slab (kg) |
|---|---|---|---|
| 3 in | 17.0 | 37.5 | 1,701 |
| 4 in | 22.7 | 50.0 | 2,268 |
| 5 in | 28.3 | 62.5 | 2,835 |
| 6 in | 34.0 | 75.0 | 3,402 |
| 8 in | 45.4 | 100.0 | 4,536 |
Normal concrete at 2,403 kg per m³.
Concrete formulas by shape
All measurements in feet; divide inches by 12 first. Results are in cubic feet.
- Slab
- length × width × thickness
- Round slab
- π × (diameter ÷ 2)² × thickness
- Continuous footing
- total length × width × depth
- Pad footing
- length × width × depth × number of footings
- Monolithic slab
- length × width × thickness + perimeter band × (edge depth − thickness), where perimeter band = length × width − (length − 2 × edge width) × (width − 2 × edge width)
- Bell footing
- π × r² × pier height + π × bell height ÷ 3 × (R² + R × r + r²), with r = pier radius and R = bell radius
- Wall
- length × height × thickness
- Column / pier
- π × (diameter ÷ 2)² × height
- Post hole
- (hole area − post area) × depth; round hole π × (diameter ÷ 2)², square hole width²
- Tube / ring
- π × [(outer ÷ 2)² − (inner ÷ 2)²] × height
- Curb & gutter
- [curb depth × (curb height + flag thickness) + gutter width × flag thickness] × length
- Steps (solid, n steps)
- width × rise × run × (1 + 2 + … + n). With a landing, the landing is the top step: width × rise × [run × (1 + … + (n − 1)) + landing depth × n]
Cubic yards = cubic feet ÷ 27. Cubic metres = cubic feet ÷ 35.31.
Frequently asked questions
How much does a cubic metre of concrete weigh?
About 2,400 kg, or 2.4 tonnes. We use 2,403 kg (150 lb per cubic foot), the same figure as the calculator.
How much does a cubic yard of concrete weigh?
About 1,837 kg, or 4,050 lb: a little less than a cubic metre, since a yard is 0.76 m³.
How much does a 4 inch slab weigh per square foot?
About 22.7 kg (50 lb) per square foot; 34.0 kg at 6 inches.
Does reinforced concrete weigh more?
A little: with rebar it is often taken as about 2,500 kg per cubic metre. Lightweight concrete is much lighter, roughly 1,400 to 1,850 kg.
About the prices