How to calculate concrete
- Measure length and width. In metres, inside the formwork. Split an L-shaped slab into two rectangles.
- Pick the thickness. In millimetres: 100 mm is common for sheds, garages and driveways.
- Multiply. Length × width × (thickness ÷ 1,000) gives cubic metres.
- Add 5–10% extra. Ground is never perfectly level and formwork flexes.
- Bags or readymix. Divide by 0.0094 for 20kg bags. Above 2–3 m³, a readymix truck saves a lot of mixing.
Worked example: a 6 × 6 m garage slab, 100 mm thick
- Volume: 6 × 6 × 0.1 = 3.60 m³. Plus 5%: 3.78 m³.
- That is 404 bags of 20kg premix, over 7 tonnes to mix by hand.
- Readymix: order 3.8 m³, above the usual 3 m³ minimum.
Concrete for common slab sizes
| Slab | Thickness | m³ | 20kg bags |
|---|---|---|---|
| 2 × 2 m | 75 mm | 0.32 | 34 |
| 2 × 2 m | 100 mm | 0.42 | 45 |
| 3 × 3 m | 75 mm | 0.71 | 76 |
| 3 × 3 m | 100 mm | 0.95 | 101 |
| 4 × 3 m | 75 mm | 0.95 | 101 |
| 4 × 3 m | 100 mm | 1.26 | 135 |
| 6 × 3 m | 75 mm | 1.42 | 152 |
| 6 × 3 m | 100 mm | 1.89 | 202 |
| 6 × 6 m | 75 mm | 2.84 | 303 |
| 6 × 6 m | 100 mm | 3.78 | 404 |
| 9 × 6 m | 75 mm | 4.25 | 455 |
| 9 × 6 m | 100 mm | 5.67 | 606 |
Includes 5% extra for waste. 20kg bags at about 0.0094 m³ each (Australian Builders states 0.01 m³).
Concrete formulas by shape
All measurements in metres; divide millimetres by 1,000 first. Results are in cubic metres.
- Slab
- length × width × thickness
- Round slab
- π × (diameter ÷ 2)² × thickness
- Monolithic slab
- length × width × thickness + perimeter band × (edge depth − thickness), where perimeter band = length × width − (length − 2 × edge width) × (width − 2 × edge width)
1 m³ = 1,000 litres.
Frequently asked questions
How many bags of concrete for a 3m x 3m slab?
At 100 mm thick it is 0.9 m³, or 0.95 m³ with 5% extra: 101 bags of 20kg premix.
How many square metres does 1m³ of concrete cover?
10 m² at 100 mm thick, 13.3 m² at 75 mm and 8 m² at 125 mm.
How many mesh sheets do I need?
Open "Reinforcement for slabs" in the calculator: it counts 6.0 × 2.4 m sheets with a 225 mm overlap for your exact slab. Check the overlap and the mesh type on your plans.
Should a slab have a road base under it?
Most do: 75–100 mm of compacted road base or crushed rock under the slab. Turn on "Gravel base" in the calculator to get the volume and, with your quarry's weight, the tonnes.
About the prices
Costs are estimated ranges with source and date, never a quote. Enter your local prices under "Use your own prices", or read how we estimate prices.